DATA CENTERS - BBVA
DATA CENTERS - BBVA
DATA CENTERS - BBVA - Tres Cantos, Madrid
BBVA
Sector
Technological. Datacenters
Bovis services
Construction Management
Construction cost
€ 120 M
Finish date
2011 / 2015
PROJECT DESCRIPTION
Main Project data:

Data Center II building (DPC +offices) 
  • 49,167 sqm above ground (6 stories)
  • Data Center II 1,500 sqm + 16,678 sqm (TIER IV)
  • 1,8 Kw / sqm
  • PUE: 1,8

Data Centre I building 
  • 17,193 sqm above ground (5 stories)
  • Data Centre I : 1,500 sqm + 7,122 sqm (TIER IV)
  • 2 Kw / sqm
  • Adiabatic cooling system for IT room
  • LEED GOLD for new construction