NEW HANGAR FOR ARIANE 6 MANUFACTURING
NEW HANGAR FOR ARIANE 6 MANUFACTURING
NEW HANGAR FOR ARIANE 6 MANUFACTURING - Madrid
AIRBUS
Sector
Industrial
Bovis services
Project Management
Construction cost
€ 20 M
Finish date
2018
PROJECT DESCRIPTION
The project consists of a new factory to produce components of the new Ariane 6 rocket, which means a huge production volume, crane loads, autoclave length, fiber placement machine, more space for logistics, new assembly areas and corresponding tools. Its objective is to build an industrial plant at the highest technical level and also with a representative and emblematic image.

The New Space Complex was developed in two phases. The first phase comprised the new hangar for Ariane 6 and the second phase comprised the space headquarters and a new hangar attached to the Ariane 6.

Main project data:
  • Plot area: 75,000 m2
  • First phase built area: approx. 18,000 m2
  • The Hangar has an area of ​​3,500 m² as a "clean room". The industrial area is 13,500 m².
  • Annex building of 800 m² for offices, technical rooms and ancillary spaces